Since our Capital Campaign began a couple of years ago, many of the targeted improvements have been implemented including the following:

New Boiler in Main Church
Air Conditioning in Main Church
Removal of Steeple / Roof repair
New Hardwood flooring in Rectory
Interior Painting of Rectory
New Door on Chapel
Architectural & Construction Plans for Universal Access
Town approval for Universal Access
Awarding of buidling contractor

 

 


 
    constnews  
     

May 12, 2011
We are very happy to let everyone know that we are now accessible. We have a working elevator and railings on the ramp so that we finally can give access to our friends and parishioners who are in wheelchairs or who have trouble with stairs. All of the work on the church is complete, with the exception of some minor details that need to be finished. We welcome you all to come and worship. On June 5th we will have a small celebration, without the bishop who will come to dedicate the new building in October. We hope you can join us this Sunday and again on the 5th.

April 21, 2011
The end is in sight! While we are still waiting for state approval of our elevator, we have moved pews to make a space for wheelchairs and to facilitate movement around the altar railing. The church is clean and shiny. All the rest rooms have new soap and paper dispensers and are ready for use, with the two new ones completely accessible. The choir is settling into the new vesting room and the new closet is ready for coats. We have noticed that two or three of our pew ends could use some repair of the wood laminate on their facades. If any one has the skill to do this with wood putty or stain, we would love your help! Please let us know. Outside, the plaza is finished and railings will be coming very soon. Many new plants are in, with others to come. The Garth has been reseeded with grass.

March 17, 2011
Work is moving along.. The light fixtures are in, including two new mini hanging lights in the Nar- thex and lights in all the new rooms. Switches are in and working. Plumbing fixtures are in and con- nected, and the plumbing passed inspection. Tile floors are in. The glass is in the nursery. Painting is finished. The elevator is installed, but still needs adjusting. Millwork for the narthex and the choir room should be in soon. Next step is to pass the electrical, elevator and fire alarm inspections.

Outside, the ramp brick is in as is most of the new brick. The work site been cleaned up in preparation for the rest of the outside work. Concrete steps are poured. The end is almost in sight! Soon we will need lots of volunteers for a massive cleaning. Almost there, time to think about what we all can do to pitch in and help.

March 6, 2011
We now have doors hung, tile laid on the bathroom floors, and the elevator installed. The glass is now in the nursery window. The elevator is a big step forward. Painting has begun. Once the walls are painted, light fixtures and switches will be put in. Slow but steady progress!

January 26, 2011
We're making progress! Our Episcopal red doors have been installed, as have the
windows, and bricks are slowly being put
on, depending on the weather. The roof is finished The vestibule is built. Inside, the
interior framing is up, the elevator shaft in
cut in and the delivery of the elevator is scheduled for next week. Plumbing and electrical roughing out should be done this week.

Things are slowly progressing, with the inside expected to be finished by March and the out- side in the Spring when we get a thaw. Again, thank you for your patience!

January 6, 2011
Construction is moving along now, after a long delay caused by the mason, who has
been replaced. The interior work should be done by mid February. Once we have that done the contractor, David Visbeen, will be able to get a temporary Certificate of
Occupancy so that we'll be able to use the finished new areas. Which means we can move things back to where they belong and clean up the parish hall. The elevator shaft has been cut out and the elevator is being made. Floors are in, including the basement. The exhaust system in the balcony attic has been removed.


The exterior part of the renovation, the ramp, steps and plaza, will take longer because it is dependent on weather. If it remains above freezing it may be finished sooner than the Spring; if there's a lot of snow and cold temperatures it will take until then. Brick work is being done by the ramp. Concrete was poured for the elevator lobby and stair bulkheads. Roof panels were delivered and roofing has begun. The aluminum and glass windows are being fabricated.
Thank you to everyone for your patience!


Eileen Wagner

constructionClick here to see some of the latest photos of our Barrier Free construction project




 


reardoors
Rear Parish Hall Entrance

sidedoor
Side Entrance (Berkeley Place)


frontcont1dig1

 
      propose  
      Below are some renderings of the proposed design for our exciting new barrier free access. The project includes an elevator, exterior ramp and rest room facilities on the main floor. There are several other improvements in the plan that benefit all of us as well. Click on any of the images to download a PDF. The design is by Callori Architects of Leonia, NJ, all rights reserved.

     
     

front-524

Front Elevation


 

 

side-524

Side Elevations


 

plan-524

Main Floor plan


 

 

site-524

Site Plan

 
         
         
             